Completing the construction ahead of schedule, American Transmission Co. (ATC) recently placed into service 75 miles of a 345 kV power line between the Werner West Substation near New London to the Gardner Park Substation adjacent to the Weston Power Plant in Wisconsin.

Construction work is continuing in Shawano County between the Highway 22 and White Clay substations in Washington, Wis. That segment is the last portion of the Morgan-Werner West line and is scheduled for an on-time completion later this year. Previously this year, a new 138 kV line was energized from Werner West to the Badger Substation, located adjacent to the Highway 22 facility.

The two new lines are needed to more fully support a new generator at the Weston Power Plant that went into service last year and to relieve congestion on lines in and around the Green Bay and Fox Valley areas, according to ATC. The Public Service Commission (PSC) of Wisconsin authorized the projects at a combined cost of $263 million, within a 10% window.

In related news, the PSC has approved ATC's application to rebuild the 18-mile, 69,000-volt electric transmission line that connects the Brodhead Substation and South Monroe Substation in Monroe, Wis. The new line will make a vital improvement in the reliability of the electric transmission system serving the area, according to ATC. The age and condition of the existing line necessitated the rebuild.

The new line will follow the route of the existing line, and the work will involve installing new poles, wires and insulators. Construction is scheduled to begin late next year and is projected to continue through summer 2011.

SOURCE: American Transmission Co.

Mortenson Construction_id2024

Trachte Inc._id1770
Latest Top Stories

Canadian Wind Industry Urges For More Federal Support

The Canadian Wind Energy Association says the country's federal government, once a big industry supporter, should again back wind power.


Wind And Solar Helped California Grid During Challenging Summer

According to the California Independent System Operator, the state suffered from heat waves and drought this year, and wind power played a "significant role" in keeping the lights on.


Recapping The Wind Industry's Third-Quarter Deals

Mercom Capital Group recaps investment and merger and acquisition activity during July, August and September.


Yearly Installed Capacity Figures Already Beat 2013 Numbers, More Wind On The Way: AWEA

While the American Wind Energy Association (AWEA) lobbies Congress to extend the production tax credit, the association notes wind projects now under construction signal a vibrant 2015.


Yahoo Inks Contract To Buy Kansas Wind Power

The Internet company plans to log in to the Alexander wind project, which is being built by community developer OwnEnergy.

Canwea_id1984
Hybrid Energy Innovations 2015
Renewable NRG_id1934
BG 2015DblBox_id2032