Portland General Electric Co. (PGE) has completed construction for the remaining 76 turbines in the first-phase development at PGE's Biglow Canyon Wind Farm in Sherman County, Ore.

PGE broke ground on the project in February, and the first turbines began generating electricity for the utility's customers in October. This brings PGE's first, wholly owned and operated wind farm to an installed capacity of 125 MW of electricity. Additional phases planned for construction in 2009 and 2010 are expected to bring the facility's total generating capacity to between 400 MW and 450 MW, according to the company.

"This has been a model project, and we're very pleased to be fully online - on time and on budget," says Jim Lobdell, vice president for power operations and resources strategy at PGE. "Phase one of Biglow Canyon has taken PGE's commitment to new renewable energy resources to a new level, building on our earlier acquisition of long-term contracts for wind power from other suppliers."

PGE estimated costs of between $255 million and $265 million to acquire turbines and construct the first phase of Biglow Canyon. Although wrap-up work and final accounting is still underway, overall project costs are expected to remain within that range. Part of the cost of the project is being offset by the Energy Trust of Oregon Inc., which is contributing $6 million.



Trachte Inc._id1770
Latest Top Stories

Why States Should Adopt A Renewable Portfolio Standard

A new study analyzes the potential benefits of state renewable energy mandates, as well as recommends what such policies should include.


Sen. Reid Vows To Bring Wind PTC To A Vote By Year's End

Nevada's senior senator provides some encouragement to wind industry advocates during his annual Clean Energy Summit.


Steadily, Wind Turbine OEMs Resume R&D Investment

An increased commitment to research and development will likely lead to wind energy innovation - not to mention a likely increase in patent-protected technology.


Quebec Government Postpones Wind Power RFP; No New Date Scheduled

The request for proposals (RFP) is part of an overall 800 MW wind power tranche that will serve as a bridge to the next phase in the province's energy future.


Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?

Renewable NRG_id1934
Canwea_id1984
Future Energy_id2008
UnitedEquip_id1995