in News Departments > New & Noteworthy
print the content item

The Maine Department of Environmental Protection (DEP) has called on First Wind to prove it will still have the financial capacity to build three wind farms following a court's recent decision to deny a joint venture between the developer and Emera.

In March, the Maine Supreme Judicial Court ruled against the state Public Utilities Commission's (PUC) approval of the JV and sent the matter back to the regulator for redetermination. The decision affects four wind energy developments in Maine, all of which had a portion of their financing funded by Emera.

Construction on the Oakfield Wind project is under way. The Hancock Wind project has been approved by the DEP, but construction has not yet commenced. The Bingham Wind project application materials are now under review, and the DEP has denied the Bowers Wind project, but that decision is under appeal.

The DEP says it is concerned project financing has been affected by the Supreme Court’s decision and has requested that First Wind submit revised financial documents for three of the affected projects. The department says submission of revised financial capacity documents for the Bowers Wind project needs to wait until after the conclusion of the appeal process.

John Lamontagne, a First Wind spokesperson, says the developer has invested almost $1 billion in Maine to date and doesn’t plan on stopping there. The company will work to try and prove its financial capacity to the DEP and has every intention to move forward with all four projects.

“The Emera joint venture provides an important, but certainly not the only, source of capital for First Wind’s Northeast projects,” he explains. “For example, First Wind closed on a $75 million bond offering last week. That offering is further evidence of First Wind’s ability to raise capital from other sources and the attractiveness of these projects to investors.”

Lamontagne adds that First Wind is confident the joint venture with Emera will be successful. “The PUC has outlined a process by which they will review the joint venture, and we will follow that closely,” he says.

Mortenson Construction_id2024

Trachte Inc._id1770
Latest Top Stories

Wind And Solar Helped California Grid During Challenging Summer

According to the California Independent System Operator, the state suffered from heat waves and drought this year, and wind power played a "significant role" in keeping the lights on.


Recapping The Wind Industry's Third-Quarter Deals

Mercom Capital Group recaps investment and merger and acquisition activity during July, August and September.


Yearly Installed Capacity Figures Already Beat 2013 Numbers, More Wind On The Way: AWEA

While the American Wind Energy Association (AWEA) lobbies Congress to extend the production tax credit, the association notes wind projects now under construction signal a vibrant 2015.


Yahoo Inks Contract To Buy Kansas Wind Power

The Internet company plans to log in to the Alexander wind project, which is being built by community developer OwnEnergy.


Could Initial Offshore Wind Projects Crash New England's REC Market?

Some are concerned that the first offshore wind projects could negatively impact pricing of renewable energy credits (RECs) in New England.