in News Departments > FYI
print the content item

The California Independent System Operator Corp. (CAISO) board of governors has approved interconnection rule changes intended to enable power plant developers to downsize projects in response to economic and demand issues.

The new interconnection changes will provide an annual process beginning in October 2014 for developers to submit a request to reduce the megawatt size of their projects for any reason. To offset possible effects on other developers, downsized projects will be obligated to finance the cost of any network upgrades that resulted from the original project size. Developers modifying the size of projects will have to provide a $60,000 deposit toward the costs incurred by CAISO.

"Building wind and solar generation or any type of power plant can take five to seven years and the business climate can change significantly during that time span," says Keith Casey, CAISO's vice president of market and infrastructure development. "These enhancements to our interconnection queue enable developers to complete projects without being subjected to risks beyond their control."

Proposed projects enter the CAISO interconnection queue as part of a first step in hooking up to the high-voltage grid. CAISO engineers study the projects to determine interconnection costs and any reliability impacts. The operator says allowing flexibility in interconnection rules eliminates the threat of their interconnection agreement being terminated for failing to meet original specifications.

IowaDeptEconDevel_id1863

Trachte Inc._id1770
Latest Top Stories

Smart Community Engagement: Twelve Tips Every Wind Developer Should Know

Community engagement helps ensure a project runs smoothly, but it can also save developers money and even lead to a more successful wind industry overall.


Bird Groups Target LEEDCo's Icebreaker Offshore Wind Pilot

Two bird conservation groups that helped halt a wind project earlier this year argue that Lake Erie Energy Development Corp.'s (LEEDCo) 18 MW offshore demo poses a major risk to regional wildlife.


Report Disputes U.S. Agency's Renewable Energy Projections

A new analysis from the Sun Day Campaign says renewables are slated to provide 16% of U.S. generating capacity by 2018 - over 20 years earlier than forecast by the Energy Information Administration.


Kansas Renewables Mandate Survives Yet Another Attack, But Is It Too Early To Celebrate?

Over the past three years, some legislators have tried to either weaken or repeal the state's renewable portfolio standard, which requires Kansas utilities to reach 20% renewables by 2020.


AWEA Highlights U.S. Wind Success Stories Of 2013

Despite a 92% drop in new capacity last year, the sector still has myriad reasons to celebrate, according to a new report from the American Wind Energy Association.