in News Departments > New & Noteworthy
print the content item



By completing three wind farms in Quebec in the past four months, EDF has provided a much-needed economic boost for the region and its supply-chain partners.

With the commissioning of the company's two most recent Quebec projects - the 150 MW Massif du Sud wind project and the first phase of the 150 MW Lac Alfred wind farm - EDF EN Canada has moved closer to achieving 1 GW of installed capacity by the end of 2015 and, in doing so, helped to boost Quebec's supply chain.

EDF EN Canada, a subsidiary of EDF Energies Nouvelles, says that with a combined investment of nearly C$700 million, the two projects created more than 600 jobs during the construction phase, as well as provides 20 to 30 permanent operations and maintenance positions.

The commissioned projects come on the heels of the October 2012 commissioning of the Saint-Robert-Bellarmin project, an 80 MW wind farm located on the Canadian border between the cities of Lac-Megantic and Saint-Georges-de-Beauce.

EDF EN says Massif du Sud and Lac Alfred represent two of the seven wind energy projects the company was awarded following the 2008 and 2010 calls for power issued by Hydro-Quebec Distribution, which is buying the output from both wind farms under 20-year power purchase agreements (PPAs).

The Hydro-Quebec calls for power included strict Quebec and regional-content requirements that limited the pool of potential turbine suppliers. The PPAs’ content requirements consist of two parts.

The first element is a regional-content requirement that is a function of the [wind turbine generator] manufacturing and assembly in the region. EDF EN Canada and REpower, which is supplying the turbines for both projects, are obligated to meet those content requirements and establish the necessary manufacturing and assembly facilities to do so.

The second PPA requirement relates to Quebec content, which is a function of the overall percentage of project costs that are sourced from within the province. In order to meet this requirement, EDF EN Canada has contracted with a Quebec firm for the design and construction of the balance-of-plant facilities, and wherever possible, the company will source materials for the project from Quebec suppliers.

In addition, developers must invest a minimum of 60% of the overall project cost within the host community. Construction at the Massif Du Sud site was performed by Construction Energie Renouvelable, a consortium consisting of Construction LFG, EBC and Transelec Common. The firm has built several Quebec-based wind farms, including Cartier Energy’s 211.5 MW Gros Morne wind farm. Quebec City-based construction services provider Borea built the Lac Alfred project.

Thirty percent of turbine costs must also be incurred within the community. In order to comply with Quebec’s domestic-content requirements, REpower has partnered with wind tower manufacturer Marmen, based in Matane; LM Wind Power’s blade facility, located in Gaspesie; New Richmond-based SEG Woodward, which is providing the controllers; and Coteau-du-Lac-based Technostrobe, a provider of protective lighting systems.

The suppliers are not the only entities that are benefiting from the two projects: The municipalities hosting the projects will receive a combined annual contribution of over C$600,000, according to Alex Couture, EDF EN Canada's project development director.

With more wind farms planned for the region, local-content suppliers will benefit from the increased business, adds EDF spokesperson Daniel Giguere. He explains that the second phase of Lac Alfred - an additional 150 MW - will be commissioned by Dec. 1.

Additionally, the developer is planning a massive C$800 million Quebec wind farm that will have a nameplate capacity nearly equivalent to that of the recently completed wind farms combined. EDF is awaiting final approval from the Quebec government for that project - the 350 MW Riviere du Moulin wind farm, which is planned for a site located 200 km north of Quebec City in Charlevoix and Saguenay territories.

In order to begin the project, EDF EN needs the government to green light the final recommendations made by the environmental minister, who received a "positive report" from BAPE, Quebec's environmental public hearing board, Giguere notes.


Photo: Seventy-five REpower turbines power EDF EN Canada's 150 MW Massif du Sud wind farm, located in Quebec. Photo courtesy of Joan Sullivan, Image Verde




Trachte Inc._id1770
Latest Top Stories

Six Key Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.


IRS Issues More PTC Guidance, Easing Some Wind Industry Concerns

The Internal Revenue Service (IRS) addresses how much work is needed on a wind farm to satisfy production tax credit (PTC) eligibility.

Renewable NRG_id1934
Canwea_id1984
Tower Conference_id1965