in News Departments > New & Noteworthy
print the content item



Despite an Ontario judge's dismissal of the case, Trillium Power is forging ahead with its C$2.25 billion lawsuit against the Ontario government, as the Toronto-based developer says the October 2012 decision contained errors in points of law and evidence.

"The reason that there are appeals courts is that sometimes, judges get it wrong," John Kourtoff, Trillium's CEO, tells NAW, adding that he does not anticipate a ruling before June.

The lawsuit centers around the government's confiscation and cancellation of Trillium's proposed 600 MW TPW 1 offshore wind project as a result of the provincial government’s February 2011 decision to place a moratorium on offshore wind. The developer says it was planning to install 120 wind turbines on a site 17 km to 28 km offshore in Lake Ontario. (Siting the project further from the shoreline alleviates much of the avian impact, because 93% to 95% of such incidents happen within 1 km of the shore, Kourtoff says.)

According to Trillium, the offshore wind moratorium was issued just one hour before the company was to complete a C$22 million financing deal for the project. Furthermore, Kourtoff says, Trillium's out-of-pocket expenses for the project total C$5.3 million.

Kourtoff maintains that government's position to halt offshore wind power was politically motivated. He cites a May 2011 memorandum of understanding (MOU) between the Ontario government and Siemens Canada. The MOU sets forth a framework wherein Siemens and Ontario would work together on economic development initiatives related to both onshore and offshore wind.

The problem, Kourtoff contends, is that the MOU was executed three months after the government declared the moratorium. Such a discrepancy demonstrates that Ontario's action against offshore wind was not part of the province’s core policy action as the government's lawyers now claim, he explains.

"This is another smoking gun that demonstrates that the government's actions were in bad faith,” Kourtoff says. "The actions were undertaken within a political calculus of the 2011 Ontario election."

Trillium's lawsuit comes at an interesting time in Ontario, as several issues - ranging from electricity prices to changes in the province's landmark feed-in tariff - have come under tremendous scrutiny.

Further complicating matters is that the ruling Liberal Party is about to choose a successor to Ontario Premier Dalton McGuinty, who unexpectedly announced his resignation last October.

The good news is that Sandra Pupatello and Kathleen Wynne - two of the front-runners vying to lead Ontario's Liberal Party - both have expressed support for offshore wind.

"It won't take long for this to get fixed," Kourtoff says. "If it does, it would send a strong signal for offshore wind."



Hse SandyHook
Latest Top Stories

Post-FIT Decision, Turbine OEMs Mull Over Options For Ontario Wind Energy Market

Under political pressure, the Ontario government recently pulled the plug on its landmark feed-in tariff (FIT) program for large-scale renewable energy projects, leaving provincial suppliers and manufacturers with an uncertain future.


Continent's First Grid-Connected Offshore Wind Turbine Floats In Maine Waters

Billed as a historic day for offshore wind in North America, researchers flipped the switch on a floating prototype. This marks the first electrons from an offshore wind turbine to flow into the region's grid.


Raising The Discourse: How Wind Industry Can Help Avoid 'Climate Emergency'

Larry Schweiger, the president/CEO at the National Wildlife Federation, says the wind industry is an important ally to combat global warming, which is triggering dangerous and unprecedented weather events around the world.


The Numbers Don't Lie: U.S. Utilities Continue To Embrace Wind Energy

Last year, more than 40% of U.S. utilities reported having wind energy on their systems, proving the fact that utilities continue to integrate wind in growing numbers – and, in some cases, at unprecedented levels.


BOEM To Award Mass., R.I. Offshore Wind Leases; Pre-Qualifies Nine Developers

In July, the Bureau of Ocean Energy Management will auction nearly 165,000 acres off the coasts of Rhode Island and Massachusetts to facilitate offshore wind development.

Power Climber_id1659
SandC Electric_id1674
Renewable Energy Systems_id1171
Upwind Solutions_id1629
Trachte Inc._id484
AWEA_id
JEC Americas_id1707