Minnesota Power has completed phases two and three of the company's 292 MW Bison Wind Energy Center.

The second and third phases of the Bison project total 210 MW and are now operational. Together, Bison 2 and 3 consist of 70 3 MW Siemens direct-drive wind turbines with 265-foot towers.

The Bison project was launched in 2010 with the 82 MW Bison 1 wind farm, which consists of 31 turbines built over two years.

Minnesota Power is moving the wind energy from North Dakota to Duluth, Minn., over a 465-mile direct-current transmission line that the company purchased in 2009. That purchase enabled the utility to phase out a long-term contract to buy coal-based electricity from the Young Station in Center, N.D., and replace it with wind energy.

The final stage of the project launch involves control testing that demonstrates that the Bison project can function as a “wind park,” with all three phases working together. The Midwest Independent Transmission System Operator will be involved in integrating the completed wind park into the regional power grid.



Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015