Officials from the U.S. Department of the Interior's Bureau of Land Management (BLM) and the U.S. Forest Service have signed records of decision (RODs) approving a right of way across federal land for the Sigurd to Red Butte No. 2 - 345 kV Transmission Line Project, which could provide key grid access for wind energy projects in the region.

The BLM says the transmission line comes in response to anticipated load growth in southwestern Utah, and will provide approximately 600 MW when it is complete.

The signing of the RODs for this project will allow PacifiCorp (doing business as Rocky Mountain Power) to construct, operate and maintain a single-circuit, alternating-current, 345 kV overhead transmission line. The transmission line would run approximately 170 miles from the existing Sigurd Substation near Richfield, Utah, to the existing Red Butte Substation in Washington County, Utah. The requested right-of-way width for the construction and operation of the line on federal lands is 150 feet.

Approximately 113 miles (67%) of the transmission-line route would be located on lands administered by three BLM-Utah field offices (Cedar City, Fillmore and Richfield Field Offices) and two national forests (Dixie and Fishlake National Forest), which required that PacifiCorp request a right of way from both the BLM and the Forest Service.

The Forest Service will issue a special-use permit for the project and will sign a separate ROD. The RODs were prepared after a 30-day waiting period on the final environmental impact statement, which was released on Oct. 5.


Mortenson Construction_id2024

Trachte Inc._id1770
Latest Top Stories

Canadian Wind Industry Urges For More Federal Support

The Canadian Wind Energy Association says the country's federal government, once a big industry supporter, should again back wind power.


Wind And Solar Helped California Grid During Challenging Summer

According to the California Independent System Operator, the state suffered from heat waves and drought this year, and wind power played a "significant role" in keeping the lights on.


Recapping The Wind Industry's Third-Quarter Deals

Mercom Capital Group recaps investment and merger and acquisition activity during July, August and September.


Yearly Installed Capacity Figures Already Beat 2013 Numbers, More Wind On The Way: AWEA

While the American Wind Energy Association (AWEA) lobbies Congress to extend the production tax credit, the association notes wind projects now under construction signal a vibrant 2015.


Yahoo Inks Contract To Buy Kansas Wind Power

The Internet company plans to log in to the Alexander wind project, which is being built by community developer OwnEnergy.

BG 2015DblBox_id2032
Renewable NRG_id1934
Hybrid Energy Innovations 2015
Canwea_id1984