Norwegian power grid operator Statnett, KfW IPEX-Bank and TenneT TSO GmbH have signed an agreement to develop and construct a subsea cable between Germany and Norway.

The high-voltage direct-current interconnector will enable renewable energy to flow between Germany and Norway and help improve the distribution of offshore wind power between the two nations.

With this cable, wind energy and solar power can be exported from Germany to Norway when there is a surplus, while Norway can export hydropower to Germany when the sun does not shine and the wind does not blow.

The integration of the Norwegian and German electricity markets, which are not currently connected, will also ensure greater grid stability in the two countries, increase market efficiency and stabilize prices between seasons, TenneT says.

The interconnector project represents an investment of approximately 1.5 billion to 2 billion euros. The three-party agreement provides for a 50:50 partnership between Norway and Germany. Norway's state-owned Statnett will own 50% of the project. On the German side, KfW and TenneT will jointly own 50% of the project via a newly established project company.

The cable is expected to be complete by late 2018.



Trachte Inc._id1770
Latest Top Stories

Canadian Wind Industry Urges For More Federal Support

The Canadian Wind Energy Association says the country's federal government, once a big industry supporter, should again back wind power.


Wind And Solar Helped California Grid During Challenging Summer

According to the California Independent System Operator, the state suffered from heat waves and drought this year, and wind power played a "significant role" in keeping the lights on.


Recapping The Wind Industry's Third-Quarter Deals

Mercom Capital Group recaps investment and merger and acquisition activity during July, August and September.


Yearly Installed Capacity Figures Already Beat 2013 Numbers, More Wind On The Way: AWEA

While the American Wind Energy Association (AWEA) lobbies Congress to extend the production tax credit, the association notes wind projects now under construction signal a vibrant 2015.


Yahoo Inks Contract To Buy Kansas Wind Power

The Internet company plans to log in to the Alexander wind project, which is being built by community developer OwnEnergy.

Canwea_id1984
BG 2015DblBox_id2032
Hybrid Energy Innovations 2015
Renewable NRG_id1934