SeaRoc has completed the installation of an offshore research and anemometry platform for the proposed 100 MW Blyth offshore wind demonstration project, to be located three nautical miles off the coast of Blyth, Northumberland, U.K.

The platform will measure the wind resource, observe marine conditions and collect marine-life data at the site. At a height of 103 meters above sea level, the meteorological mast will assess the conditions at the proposed demonstration site for turbines up to 8 MW, SeaRoc explains.

The platform has been designed for a 22-year life, and it was installed on a tripod structure in water depths of 37 meters. In addition to providing a benchmark for tenants to monitor the performance of turbines on the Blyth site, the platform provides an open-access research facility to trial new technologies and processes intended to reduce the time scales and costs of the consenting process for offshore wind.

The contract for the installation of the anemometry platform was awarded to SeaRoc earlier this year. The U.K.’s National Renewable Energy Centre submitted an application to the Marine Management Organisation in March for consent for the proposed 100 MW Blyth offshore wind demonstration site, and a decision is expected within 12 months. A competitive tendering process is also under way to select tenants for the proposed three arrays to demonstrate turbines with a blade-tip height of up to 195 meters.




Trachte Inc._id1770
Latest Top Stories

Canadian Wind Industry Urges For More Federal Support

The Canadian Wind Energy Association says the country's federal government, once a big industry supporter, should again back wind power.


Wind And Solar Helped California Grid During Challenging Summer

According to the California Independent System Operator, the state suffered from heat waves and drought this year, and wind power played a "significant role" in keeping the lights on.


Recapping The Wind Industry's Third-Quarter Deals

Mercom Capital Group recaps investment and merger and acquisition activity during July, August and September.


Yearly Installed Capacity Figures Already Beat 2013 Numbers, More Wind On The Way: AWEA

While the American Wind Energy Association (AWEA) lobbies Congress to extend the production tax credit, the association notes wind projects now under construction signal a vibrant 2015.


Yahoo Inks Contract To Buy Kansas Wind Power

The Internet company plans to log in to the Alexander wind project, which is being built by community developer OwnEnergy.