German wind turbine manufacturer Nordex says it has been installing its N117/2400 series wind turbines at the Beebe Renewable Energy project, which, when complete, will have a capacity of 81.6 MW.

The company says the first turbine was installed on Sept. 27 at the Gratiot County, Mich., site and that 17 of the 34 turbines are fully assembled. To date, 27 blade sets have been delivered to Michigan.

The project marks the start of series production of Nordex's N117/2400 nacelle at its Jonesboro, Ark., facility, as well as the beginning of series production of its NR58.5 rotor blade in Germany.

All of the blades are on their way to Michigan, and all of the turbines are expected to be installed by the end of the year.

Nordex also notes that it is planning to start production of the NR58.5 rotor blade in North America in 2013.



Trachte Inc._id1770
Latest Top Stories

Six Key Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.


IRS Issues More PTC Guidance, Easing Some Wind Industry Concerns

The Internal Revenue Service (IRS) addresses how much work is needed on a wind farm to satisfy production tax credit (PTC) eligibility.

Canwea_id1984
Renewable NRG_id1934
Tower Conference_id1965