San Diego Gas & Electric (SDG&E) says it has completed and put into service the Sunrise Powerlink, a 500 kV transmission line linking San Diego to the Imperial Valley, one of the most renewable-energy-rich regions in California.

The transmission line will initially be capable of bringing 800 MW of additional imported power - including renewable energy - into San Diego, and will eventually carry 1 GW of power.

In the near future, the Sunrise Powerlink will deliver a significant amount of wind and solar power to San Diego. Over the past three years, SDG&E has signed eight renewable energy agreements for more than 1 GW of wind and solar power from projects in Imperial County, and that renewable energy will be transmitted across the Sunrise Powerlink.

The transmission project consists of more than 110 miles of overhead 500 kV and 230 kV transmission towers and conductor, 6.2 miles of underground 230 kV cable, and a 40-acre, 500 kV transmission substation.

SDG&E and the California Independent System Operator Corp. say the transmission line is one of the important mitigation measures that will help maintain electric reliability during heat waves without power from the San Onofre Nuclear Generating Station.

The completion of the nearly $1.9 billion project culminates a rigorous, five-year-long environmental review and permitting process and 18 months of construction that encompassed both overhead and underground technology, as well as different climates and rough, remote terrain, SDG&E explains.

“The Sunrise Powerlink, which now provides the pathway for local renewable energy projects, enables us to develop Imperial County’s abundant renewable energy resources while also preserving our natural resources and native habitat,” says Imperial County Board Supervisor Gary Wyatt.


Mortenson Construction_id2024

Trachte Inc._id1770
Latest Top Stories

Recapping The Wind Industry's Third-Quarter Deals

Mercom Capital Group recaps investment and merger and acquisition activity during July, August and September.


Yearly Installed Capacity Figures Already Beat 2013 Numbers, More Wind On The Way: AWEA

While the American Wind Energy Association (AWEA) lobbies Congress to extend the production tax credit, the association notes wind projects now under construction signal a vibrant 2015.


Yahoo Inks Contract To Buy Kansas Wind Power

The Internet company plans to log in to the Alexander wind project, which is being built by community developer OwnEnergy.


Could Initial Offshore Wind Projects Crash New England's REC Market?

Some are concerned that the first offshore wind projects could negatively impact pricing of renewable energy credits (RECs) in New England.


Catching Up With The DOE's Down-Select Offshore Winners

The three recipients of key U.S. Department of Energy (DOE) funding provide updates on their offshore wind demonstration projects.

Canwea_id1984
Hybrid Energy Innovations 2015
Renewable NRG_id1934