Iberdrola says it has begun the engineering phase of its first German offshore wind farm. The 1.6 billion euro project, called Wikinger, is expected to be operational by 2016.

In total, the company is planning 11 GW of offshore wind capacity across Europe, including in the U.K. and France.

Iberdrola says the Wikinger project will enable the development and construction of up to 80 wind turbines with a total capacity of up to 400 MW. The project will be located about 30 km off the coast of the German Island of Rugen, and will cover an area of 34 square kilometers in the Baltic Sea.

U.K.-based engineers, project managers and technicians from Iberdrola’s Offshore Business division, based in Glasgow and London, will play a crucial role in the project.

The company says it is working with German authorities to ensure it has the right regulatory framework in place to enable essential grid connections to be delivered on time and to reduce the lead times for gaining planning permission and beginning construction.

Iberdrola acquired the rights to develop the project from the joint venture formed by Deutsche Erneuerbare Energien GmbH (Deutsche Bank Group) and Ventotec GmbH. At the time, the project’s preliminary construction permit contemplated floating foundations.

However, after conducting a study of the site’s technical conditions and taking into account the present stage of technological development, the company decided to use larger-scale wind turbines with jacket foundations, which are better suited for the conditions in the Baltic Sea, Iberdrola explains.

Once all of the permits are obtained - which is planned for early 2014 - the company will announce the final project timeline, with construction scheduled for 2015 and first energy export in 2016.


IOWA Economic Development id2073

Trachte_id2056
Latest Top Stories

Deepwater Hits Financial Close For Block Island Wind Farm, Expects Summer Construction

The Providence, R.I.-based offshore wind developer becomes the first to financially close on a U.S.-based offshore wind project.


More Investors Entering Tax Equity Market; Returns Holding Steady

The entry of new tax equity investors to the wind space last year re-ignited an old debate.


Report: Top 10 Turbine OEMs Had Record Year In 2014

Preliminary findings suggest Vestas reigned supreme again among the world's leading wind turbine makers. How did some of the other OEMs fare?


AWEA's Gramlich To FERC: Additional Transmission Needed Regardless Of Clean Power Plan

To further build a more balanced and reliable electricity portfolio, the U.S. needs to build more transmission capacity.


Getting A Grip On Grinding Gearboxes: Why Such Events Need Not Be Showstoppers

Despite advances in gearbox reliability - namely, from condition monitoring systems and greater design standardization - challenges remain.

Hybrid Energy Innovations 2015