The Bonneville Power Administration (BPA), Puget Sound Energy (PSE) and Seattle City Light (SCL) have signed a memorandum of agreement (MOA) aimed at improving the reliability of the regional electric grid and reducing the probability of region-wide customer power outages in the future.

The MOA includes six proposed transmission improvement projects that aim to significantly improve electric reliability for electric utility customers in the Puget Sound area. In all, the projects are estimated to cost approximately $140 million and involve either transmission-line upgrades or equipment additions at existing facilities.

"The transmission system serving the Puget Sound region is at capacity and needs to be upgraded," says Brian Silverstein, senior vice president at BPA Transmission Services. “Several decades have passed since we and the area utilities have jointly invested in large, regional bulk-power transmission projects. Now is the time to consider these projects to avoid load curtailments and potential region-wide power outages in the future.”

In developing the projects covered by the MOA, the BPA, PSE, SCL and Snohomish County Public Utility District looked to the technical work of the ColumbiaGrid’s Puget Sound Area Study Team, which has studied and analyzed the regional bulk electric transmission system for several years to help develop the “one-utility” planning approach.

When large amounts of energy are being delivered to the Puget Sound area through the Northern Intertie to Canada, oftentimes, transmission lines become congested. To relieve this congestion and avoid unplanned power interruptions to customers, BPA currently limits or curtails the amount of energy Puget Sound-area utilities and Canadian utilities can deliver across certain transmission lines. This curtailment process has been in place since fall 2007.

Energy-demand projections for the Puget Sound area and the potential for additional energy delivery from the Northwest to Canada have transmission system planners projecting increased curtailments by the end of this decade.

When the curtailments are instituted, utilities have to make changes to the generating resources providing power to the area, BPA says, which can be costly to Puget Sound-area customers and the environment. The new projects will significantly expand system capacity and minimize the need for curtailments - such as last spring’s 350 MW wind energy curtailment - and potential rolling blackouts, BPA adds.


IowaDeptEconDevel_id1863

Trachte Inc._id1770
Latest Top Stories

Report Disputes U.S. Agency's Renewable Energy Projections

A new analysis from the Sun Day Campaign says renewables are slated to provide 16% of U.S. generating capacity by 2018 - over 20 years earlier than forecast by the Energy Information Administration.


Kansas Renewables Mandate Survives Yet Another Attack, But Is It Too Early To Celebrate?

Over the past three years, some legislators have tried to either weaken or repeal the state's renewable portfolio standard, which requires Kansas utilities to reach 20% renewables by 2020.


AWEA Highlights U.S. Wind Success Stories Of 2013

Despite a 92% drop in new capacity last year, the sector still has myriad reasons to celebrate, according to a new report from the American Wind Energy Association.


Feds List New Bird Species As Threatened - Should Wind Developers Be Worried?

The U.S. Fish and Wildlife Service is designating the lesser prairie-chicken as threatened under the Endangered Species Act. An expert explains how this might affect the wind industry.


Senate Committee Passes Bill With Two-Year PTC Extension

The Senate Finance Committee has voted on a tax extenders package, which includes both the production tax credit (PTC) and investment tax credit, and sent it to the floor.

Acciona_id1907
JLG_id1900
UEA_id1896
WomenofWind_id
AWEA_id1886
bonfiglioli_id1913