Pepco Holdings Inc. (PHI) has notified the Maryland Public Service Commission and the Virginia State Corporation Commission that the company is requesting delays in the commissions' reviews of the respective applications filed by the utility's subsidiaries, Pepco and Delmarva Power, for state regulatory approval for the Mid-Atlantic Power Pathway (MAPP) transmission project.

The requests were filed following notification from PJM Interconnection that it has established a new in-service date for MAPP, a proposed high-voltage, 152-mile interstate transmission project planned to originate at the Possum Point substation in northern Virginia, traverse under the Chesapeake Bay and end at the Indian River substation in Delaware.

PJM’s notification states that the need for MAPP has moved from 2015 to the 2019-2021 time frame. However, PJM also noted that transmission planning “uncertainties could accelerate this schedule.” The letter states that PJM’s action “does not constitute a directive by PJM to cancel or abandon the MAPP project,” and also directs PHI to proceed with those development efforts “reasonably necessary to allow the MAPP project to be quickly restarted,” according to PHI.

The notification also states that PJM will be using a new stakeholder process to evaluate its transmission planning methods, which could lead to changes in PJM’s assessment of MAPP’s in-service date. PJM does not expect the new evaluation to be completed until sometime next year.

“Reliable power is critical to the economy and security of this region and the country,” says Joe Rigby, PHI’s chairman, president and CEO. “PHI remains committed to the MAPP project due to the many benefits it will provide to the region, including enhancing electric system reliability, transporting renewable wind energy from offshore to the Mid-Atlantic region and fueling economic growth.”


Trachte Inc._id1770
Latest Top Stories

Quebec Government Postpones Wind Power RFP; No New Date Scheduled

The request for proposals (RFP) is part of an overall 800 MW wind power tranche that will serve as a bridge to the next phase in the province's energy future.


Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.

Canwea_id1984
Renewable NRG_id1934
UnitedEquip_id1995
Tower Conference_id1965