Enbridge Ontario Wind Power LP, a subsidiary of Enbridge Inc., and Canadian Hydro Developers Inc., a Calgary, Alberta-based renewable energy project developer and owner, have received approval by the Ontario Ministry of the Environment for their respective environmental screening reports. By receiving the approval, both wind projects will not be required to perform individual environmental assessments.

According to Enbridge, this acceptance marks a significant step toward the construction of its proposed 182 MW wind farm, which would be located in Kincardine, Ontario, and consist of 110 wind turbines. An Ontario Municipal Board hearing to address appeals is scheduled to begin on April 23.

In addition, the ministry approved Canadian Hydro's 132 MW Melancthon II Wind Project, which is the second phase of the company's 67.5 MW Melancthon project located near Shelburne, Ontario. In accordance with the provisions of the environmental screening process, the ministry's decision will become final on April 2, unless a request is made prior to then to review the decision. If no request is made, then Canadian Hydro can submit the required statement of completion and may proceed with Melancthon II - subject to any other permits or approvals required.


Trachte Inc._id1770
Latest Top Stories

Why States Should Adopt A Renewable Portfolio Standard

A new study analyzes the potential benefits of state renewable energy mandates, as well as recommends what such policies should include.


Sen. Reid Vows To Bring Wind PTC To A Vote By Year's End

Nevada's senior senator provides some encouragement to wind industry advocates during his annual Clean Energy Summit.


Steadily, Wind Turbine OEMs Resume R&D Investment

An increased commitment to research and development will likely lead to wind energy innovation - not to mention a likely increase in patent-protected technology.


Quebec Government Postpones Wind Power RFP; No New Date Scheduled

The request for proposals (RFP) is part of an overall 800 MW wind power tranche that will serve as a bridge to the next phase in the province's energy future.


Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?