The California Public Utilities Commission (CPUC) has approved Southern California Edison's (SCE) application to build segments two and three of the Tehachapi Renewable Transmission Project. The first segment of the project was approved by the commission at the beginning of March and is pending approval by the U.S. Forest Service. (See "SCE's Tehachapi Transmission Project Receives Another Approval.")

When all 11 phases are developed, the Tehachapi project will include a series of new and upgraded high-voltage transmission lines capable of delivering 4,500 MW of electricity from wind farms and other generating sources that are proposed for northern Los Angeles and eastern Kern counties, SCE says.

Segments two and three include a new 21-mile, 500 kV transmission line connecting SCE's existing Antelope and Vincent Substations; two new substations to be named Windhub and Highwind, located near Mojave and Monolith; a new, 25.6-mile, 500 kV transmission line connecting SCE's existing Antelope Substation with the proposed Windhub Substation; and a new, 9.6-mile, 220 kV transmission line connecting Windhub Substation with Highwind Substation.

According to SCE, the new lines are expected to be operational in early 2009. The company will file an application next June to build the remaining segments.


Trachte Inc._id1770
Latest Top Stories

Wind And Solar Are Catching Up With Nuclear Power, Says Report

A new report from the Worldwatch Institute says nuclear energy's share of global power production is steadily shrinking. Meanwhile, renewables' share keeps growing.


Could New Desert Plan Spell The End Of California Wind Energy Development?

The California Wind Energy Association says it is disappointed with the draft Desert Renewable Energy Conservation Plan, which was recently released by state and federal agencies.


New U.S. House Bill Includes Wind PTC Extension

U.S. representatives have introduced the Bridge to a Clean Energy Future Act of 2014, which would extend the production tax credit (PTC) and other provisions through 2016.


Utility-Scale Wind And Solar Keep Getting Cheaper

A new study measures the levelized cost of energy from various technologies and suggests that the costs of utility-scale wind and solar power are catching up with those of traditional sources, even without subsidies.


The Song Remains The Same: Ontario Seeks More Science Before Lifting Offshore Ban

The Ontario government says the nearly four-year-old offshore wind moratorium will remain in place until the province fully understands the technology’s impact on the environment.

Renewable NRG_id1934
Canwea_id1984
Future Energy_id2008