Pepco Holdings Inc. (PHI) has announced that a review by the regional power grid operator has determined that the company's planned Mid-Atlantic Power Pathway (MAPP) transmission line remains critical to long-term electrical reliability in southern Maryland and on the Delmarva Peninsula. However, a one-year delay was recommended for the line's in-service date due to a reduced, near-term load forecast for the region.

The grid operator, PJM Interconnection, recommended moving the in-service date for MAPP from 2013 to June 1, 2014. The downturn in the economy and resulting reduction in power demand factored into its recommendation. PJM projects future electricity demand will increase as the economy recovers and says that MAPP is essential to maintaining long-term electric reliability.

"The MAPP project continues to be a critical part of the solution in addressing future energy demand in southern Maryland, on the Delmarva Peninsula and throughout the Mid-Atlantic region," says William M. Gausman, senior vice president for asset management and planning for PHI. "It takes years to finalize approvals and construct major infrastructure projects like this line. Because of the long lead time for completion, we do not anticipate this decision to significantly affect our ongoing efforts to responsibly move forward with the critical activities, including the regulatory and permitting process for MAPP."

According to Gausman, PJM has also reviewed the need for the section of the line that would run from Delmarva Power's Indian River substation near Millsboro, Del., to Salem, N.J., and has decided to move this portion of the line into its "continuing study" category.

This means that the reconfigured MAPP line will now extend approximately 150 miles from northern Virginia, across southern Maryland and the Chesapeake Bay, and terminate at Indian River. The change would likely reduce the total project cost from $1.4 billion to $1.2 billion.

The use of an advanced, high-voltage, direct-current system for a portion of the MAPP project is an important reason that the line will still be able to address expected electricity reliability violations on the Delmarva Peninsula and the Mid-Atlantic region.

This direct-current line will connect to the existing transmission system that has undergone extensive upgrades over the past few years.

SOURCE: Pepco Holdings Inc.


Trachte Inc._id1770
Latest Top Stories

Sen. Grassley Makes Another Legislative Push For Wind PTC Extension

U.S. Sen. Chuck Grassley, a long-time wind power advocate, recently made an effort to bring attention to the importance of a production tax credit extension.


Alberta Breaks Wind Power Record, Then Does It Again

Last week, the Alberta Electric System Operator recorded new wind production peaks in the Canadian province - highlighting how well the grid integrated the renewable energy.


Federal Appeals Court Finds Obama's Wind Farm Decision Unconstitutional

A federal appeals court ruled that the U.S. government violated the constitutional rights of Chinese-owned Ralls Corp. when ordering the divestment of four Oregon wind farms.


Renewables Make Up Over 50% Of New U.S. Power In First Half Of 2014

According to a recent government report, renewable energy sources, such as wind and solar, continue to dominate new electric generating capacity.


Suzlon Facility Lends Key Assist In Developing 'The Wind Technicians Of Tomorrow'

The turbine manufacturer’s Elgin, Ill.-based training facility is the culmination of a program that puts a new twist on a proven method of instruction.

Navigant_id1983
Renewable NRG_id1934
Canwea_id1984