in News Departments > Projects & Contracts
print the content item

Canadian Hydro Developers Inc.'s Wolfe Island Wind Project began commissioning the first of its 86 wind turbines. The $475 million facility will double Canadian Hydro's operations. The project is on target to begin commercial operations by the end of June, and some of the wind turbines have started turning and generating electricity.

"Our staff and contractors did an incredible job getting all the wind turbines erected by mid-April," said Geoff Carnegie, Development Manager of Canadian Hydro's wind division.

"All the required infrastructure and testing have been approved by the Independent Electricity System Operator, Electrical Safety Authority and Hydro One Networks Inc. to make the energization of the Wolfe Island Transformer Station possible last week," says Geoff Carnegie, development manager of Canadian Hydro's wind division.

Carnegie explained that the first three electrical circuits, representing 43 of the 86 wind turbines, are ready for integration into the provincial electrical system and are expected to be fully commissioned, generating electricity to the grid this month, with the remaining three circuits to follow throughout May and June. Once completed, the project is expected to produce 197.8 MW of power.

SOURCE: Canadian Hydro Developers Inc.



Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015