Canadian Hydro Developers Inc., through its wholly owned subsidiary, Canadian Renewable Energy Corp., says that its 197.8 MW Wolfe Island Wind Project is expected to achieve a target in-service date of June 30. The previously announced date was March 31.

Harsher than expected winter weather conditions have pushed back the project completion, and as a result, the project schedule has been revised for the remainder of the winter - reducing the total number of turbines erected each week based on performance to date.

The updated schedule has resulted in a revised expected capital cost from $450 million to $475 million - a 6% increase. The $25 million capital cost increase will be funded through available internal sources.

In spite of the various winter weather challenges, construction continues to progress at Wolfe Island, with 45 of the 86 turbines fully erected and the laying of the 7.8 km submarine cable completed. All turbines and components have been delivered to Wolfe Island, and work is under way on the interconnection to the mainland. It is expected that the first two of six electrical circuits, which comprise approximately 30 wind turbines, will provide energy to the provincial grid by April.

"Our staff, contractors and subcontractors have performed admirably in the face of adverse working conditions, and we are proud of them for all that has been accomplished to date," says John Keating, CEO of Canadian Hydro.

The project is owned and will be operated by Canadian Hydro. It is expected to generate approximately 594 GWh annually of renewable energy. The project has a 20-year renewable energy supply contract with the Ontario Power Authority for the purchase of electricity and renewable energy certificates and will receive funding under the federal ecoENERGY for renewable power program.

SOURCE: Canadian Hydro Developers Inc.




Trachte Inc._id1770
Latest Top Stories

Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.

Renewable NRG_id1934
Canwea_id1984
UnitedEquip_id1995
Tower Conference_id1965