in News Departments > Projects & Contracts
print the content item

Canadian Hydro Developers Inc., through its wholly owned subsidiary, Canadian Renewable Energy Corp., says that its 197.8 MW Wolfe Island Wind Project is expected to achieve a target in-service date of June 30. The previously announced date was March 31.

Harsher than expected winter weather conditions have pushed back the project completion, and as a result, the project schedule has been revised for the remainder of the winter - reducing the total number of turbines erected each week based on performance to date.

The updated schedule has resulted in a revised expected capital cost from $450 million to $475 million - a 6% increase. The $25 million capital cost increase will be funded through available internal sources.

In spite of the various winter weather challenges, construction continues to progress at Wolfe Island, with 45 of the 86 turbines fully erected and the laying of the 7.8 km submarine cable completed. All turbines and components have been delivered to Wolfe Island, and work is under way on the interconnection to the mainland. It is expected that the first two of six electrical circuits, which comprise approximately 30 wind turbines, will provide energy to the provincial grid by April.

"Our staff, contractors and subcontractors have performed admirably in the face of adverse working conditions, and we are proud of them for all that has been accomplished to date," says John Keating, CEO of Canadian Hydro.

The project is owned and will be operated by Canadian Hydro. It is expected to generate approximately 594 GWh annually of renewable energy. The project has a 20-year renewable energy supply contract with the Ontario Power Authority for the purchase of electricity and renewable energy certificates and will receive funding under the federal ecoENERGY for renewable power program.

SOURCE: Canadian Hydro Developers Inc.




Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015