The Federal Energy Regulatory Commission (FERC) has issued an order granting the California Independent System Operator Corp. (CalISO) permission to launch the first part of a two-step process to clear a backlog that has hindered renewable projects attempting to connect to the California grid.

CalISO was given approval to waive certain rules and timelines for handling requests from new power plants seeking interconnection with the transmission system. As a result, CalISO can immediately begin to reduce the backlog of projects in its queue.

As part of this transition, CalISO will be allowed to create three study groups:

- a grandfathered serial study group that would give expedited treatment to projects already in the queue,

- a transition cluster, comprising non-grandfathered projects submitted on or before June 2, 2008, and

- an initial cluster for projects submitted on or after June 3, 2008.

The second step in the process to address these issues will be gaining FERC approval for a full-scale generator interconnection process reform proposal.

SOURCE: California Independent System Operator Corp.


Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015