NorthWestern Corp., doing business as NorthWestern Energy, has submitted the Mountain States Transmission Intertie (MSTI) major facility siting application (MFSA) with the Montana Department of Environmental Quality (DEQ).

NorthWestern Energy proposes to construct, operate and maintain the approximately 400-mile, 500 kV transmission line to address the requests for transmission service from customers and to relieve constraints on the high-voltage transmission system in the region. The new transmission line is expected to run from a new substation near Townsend, Mont., to a substation near Midpoint, Idaho.

"The filing of this application takes us one step closer toward the realization of the Mountain States Transmission Intertie project, which is designed to facilitate generation development in Montana," says Dave Gates, vice president of wholesale operations at NorthWestern Energy, adding that renewable generation projects in Montana would benefit from new transmission.

The Montana DEQ has 30 days to complete the review of the MFSA application and notify NorthWestern Energy of any additional information or requirements. Once the MFSA process is completed, NorthWestern Energy will proceed with an environmental review - including an environmental impact statement - under the Montana Environmental Policy Act and National Environmental Policy Act, and other various approvals and permits. This process is expected to begin in late August with additional public scoping meetings scheduled in September.

SOURCE: NorthWestern Energy



Trachte Inc._id1770
Latest Top Stories

Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.


IRS Issues More PTC Guidance, Easing Some Wind Industry Concerns

The Internal Revenue Service (IRS) addresses how much work is needed on a wind farm to satisfy production tax credit (PTC) eligibility.


Embryonic No More: U.S. Offshore Wind Industry Gaining Momentum

After a decade of fits and starts, the industry is moving closer to installing the first generation of wind projects off the country's shores.


AWEA: U.S. Installs 853 MW Of Wind In First Half Of 2014

The American Wind Energy Association (AWEA) reveals the U.S. industry's progress thus far this year and underscores the importance of policy certainty.

Canwea_id1984
Renewable NRG_id1934
Tower Conference_id1965