Houston-based Horizon Wind Energy has selected Chicago-based Sargent & Lundy LLC to design the 345 kV interconnection switchyards, the 345/34.5 kV project substations, the 345 kV transmission lines and 34.5 kV underground collector systems for the first phases of the Top Crop Wind Farm project in Illinois and the Meadow Lake Wind Farm in Indiana. The first phases of Top Crop and Meadow Lake will have a nameplate capacity of 300 MW and 200 MW, respectively.

The Top Crop Wind Farm will connect to an existing Commonwealth Edison 345 kV transmission line. The Meadow Lake Wind Farm will connect to an existing American Electric Power 345 kV transmission line. Both projects will have provisions for expansion.

Sargent & Lundy's scope of work for these projects includes electrical and structural engineering, grading and drainage design, and support for procurement of major materials and equipment.

The company's scope also includes coordination with the interconnecting utilities in regard to standards and protection and control schemes. The schedule for engineering and procurement supports an April 2009 start of construction and a project in-service date of November 2009 for both wind farms, according to the company.

SOURCE: Sargent & Lundy LLC


Advertisement

Trachte_id2056
Latest Top Stories

More Investors Entering Tax Equity Market; Returns Holding Steady

The entry of new tax equity investors to the wind space last year re-ignited an old debate.


Report: Top 10 Turbine OEMs Had Record Year In 2014

Preliminary findings suggest Vestas reigned supreme again among the world's leading wind turbine makers. How did some of the other OEMs fare?


AWEA's Gramlich To FERC: Additional Transmission Needed Regardless Of Clean Power Plan

To further build a more balanced and reliable electricity portfolio, the U.S. needs to build more transmission capacity.


Getting A Grip On Grinding Gearboxes: Why Such Events Need Not Be Showstoppers

Despite advances in gearbox reliability - namely, from condition monitoring systems and greater design standardization - challenges remain.


How Wind Energy Can Meet EPA Clean Power Plan Requirements

According to the American Wind Energy Association, wind power is a cost-effective solution for complying with the environmental effort.

Hybrid Energy Innovations 2015