in News Departments > New & Noteworthy
print the content item

The Federal Energy Regulatory Commission (FERC) has directed regional transmission organizations (RTOs) and independent system operators (ISOs) to report on the status of their efforts to improve the processing of their interconnection queues.

The request follows a Dec. 11, 2007, technical conference on interconnection queue practices, at which participants complained of transmission providers' delays in processing interconnection queues, particularly in RTO and ISO regions that are attracting significant new entry into generation markets, particularly in regions where the industry is working to meet state renewable portfolio standards.

FERC is giving the RTOs and ISOs 30 days from the date of the order, issued on March 20, to provide information on a variety of matters, including the current size of their queues, the current timeframes for processing those requests and the nature and extent of any problems that have led to any backlogs. Their reports also must explain the status of stakeholder discussions on queue reform and provide a schedule for selecting and implementing any necessary reforms, including a target date for filing any necessary tariff amendments or waivers.

To help them gather that information, FERC is offering guidance that breaks down the reforms into those that can be implemented quickly and without any tariff revisions, and those that require tariff changes.

The FERC guidance document states that reforms made without tariff changes could include increasing the staff available to work on interconnection studies; adopting more efficient modeling for feasibility studies or system impact studies; or performing a single system impact study for a cluster of interconnection requests.


Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015