Judge Bruce E. Priddy, from the 116th Civil District Court, has reversed an earlier jury verdict and ruled that Dallas-based TXU Corp. is not entitled to any damages in a contract dispute with wind farm operator FPL Energy, according to Lynn Tillotson & Pinker, a Dallas-based law firm that represented FPL.

The dispute centered on claims that Florida-based FPL Energy had not supplied levels of energy from its three wind farms - Indian Mesa and Pecos I and Pecos II in west Texas - as agreed upon in a contract. The wind farms counter-claimed, alleging that they could not satisfy the contract because TXU intentionally had clogged high-voltage transmission lines, preventing the delivery of electricity produced by FPL Energy's wind turbines.

The contract dispute began in 2004, and the lawsuit originally sought $46 million in damages and interest.

In his ruling, Priddy agreed with arguments presented by FPL Energy's lead counsel, Mike Lynn, who asserted that TXU suffered no losses because the utility had purchased or produced electricity to compensate for electricity that the wind farms had not supplied. Since TXU had effectively "covered" for any deficiencies in FPL's supply of electricity, the judge ruled that TXU is entitled to nothing under the Uniform Commercial Code.


Trachte Inc._id1770
Latest Top Stories

Quebec Government Postpones Wind Power RFP; No New Date Scheduled

The request for proposals (RFP) is part of an overall 800 MW wind power tranche that will serve as a bridge to the next phase in the province's energy future.


Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.

Canwea_id1984
Renewable NRG_id1934
UnitedEquip_id1995
Tower Conference_id1965