The Cape Cod Commission (CCC) has voted to deny an application from Cape Wind for a submarine and upland cable system to transmit power from Cape Wind's proposed offshore wind farm in Nantucket Sound. The CCC's decision document notes that the denial was due to Cape Wind's refusal to allow the CCC additional time to obtain missing information that would be necessary to make a decision on the project.

"Should Cape Wind provide the information requested by the commission as part of its [Development of Regional Impact (DRI)] review," the CCC writes, "the commission can continue with its review of the project subject to a resubmitted DRI application. The commission anticipates that some of the information it has requested but not received may be prepared for or contained in the [Minerals Management Service environmental impact statement]." The CCC adds that it is willing to reconsider the project if that information is available.

Representatives of Cape Wind issued the following statement in response to the CCC's decision:

"The Commission's denial, based not on the merits but on claims that Cape Wind provided insufficient information, does not square with the record. Since 2001, Cape Wind has been providing extensive information about these cables to the Cape Cod Commission and state and federal agencies. In fact, in 2005, the Massachusetts Energy Facilities Siting Board approved Cape Wind's electric cable because it found that Cape Wind would provide needed renewable electricity, deliver significant air quality benefits, lower electric costs and increase electric transmission reliability."

Cape Wind says it will seek a method to override the CCC's "attempt to delay important renewable energy benefits for Massachusetts citizens."



Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015