Starwood Energy Group Global, a Connecticut-based private investment firm, has completed agreements to finance and construct the second phase of its 377 MW Stephens Ranch wind farm complex in Texas.

The 165 MW Stephens Ranch II project is located 45 miles south of Lubbock and will use GE 1.7-100 turbines. Wanzek Construction will build the project, with completion scheduled for mid-2015.

Affiliates of Citi, Morgan Stanley and MUFG have committed to invest tax equity in Stephens Ranch II, and affiliates of Starwood Energy Group have committed 100% of the cash equity. Affiliates of Citi, Morgan Stanley and MUFG are also providing a non-recourse construction debt facility (including a letters of credit facility) totaling approximately $207 million. Affiliates of MUFG will act as administrative agent, collateral agent, and depositary bank.

"We are pleased to have assembled a team of very experienced partners for this project," says Himanshu Saxena, managing director of Starwood Energy Group. "We remain committed to this sector as we continue to look for new investment opportunities. Continued federal support for wind projects is a key enabler for such investments as the nation transitions to a greener economy."

An investment affiliate of Starwood acquired the Stephens Ranch scheme from Mesa Power in 2013, and the company closed financing on the first phase of the project in January.






Advertisement

Trachte_id2056
Latest Top Stories

More Investors Entering Tax Equity Market; Returns Holding Steady

The entry of new tax equity investors to the wind space last year re-ignited an old debate.


Report: Top 10 Turbine OEMs Had Record Year In 2014

Preliminary findings suggest Vestas reigned supreme again among the world's leading wind turbine makers. How did some of the other OEMs fare?


AWEA's Gramlich To FERC: Additional Transmission Needed Regardless Of Clean Power Plan

To further build a more balanced and reliable electricity portfolio, the U.S. needs to build more transmission capacity.


Getting A Grip On Grinding Gearboxes: Why Such Events Need Not Be Showstoppers

Despite advances in gearbox reliability - namely, from condition monitoring systems and greater design standardization - challenges remain.


How Wind Energy Can Meet EPA Clean Power Plan Requirements

According to the American Wind Energy Association, wind power is a cost-effective solution for complying with the environmental effort.

Hybrid Energy Innovations 2015