EDF Renewable Energy says its 161 MW Spinning Spur II wind project in Texas has reached its commercial operation date (COD).

According to EDF, Spinning Spur II commenced construction of 87 GE 1.85 MW, 87-meter rotor wind turbines 40 miles west of Amarillo in June 2013. The company's renewable services unit will provide long-term operations and maintenance for the facility, balance of plant, project oversight and 24/7 remote monitoring from its operations control center.

EDF notes the project is one of the first to feed into the new Competitive Renewable Energy Zones transmission infrastructure that enables access to the renewable resources of West Texas and the Texas Panhandle and delivery of the wind energy resource to the high electricity demand areas in the state.

The company also announced the close of structured equity financing from GE Energy Financial Services and MUFG Union Bank NA. Although financial details were not disclosed, the COD milestone signifies that UBS International Infrastructure Fund now has a 50% equity stake in the project.

Mortenson Construction_id2024

Trachte Inc._id1770
Latest Top Stories

Are Fitch Ratings' Claims About Wind Farm Underperformance Unfounded?

A recent report from Fitch Ratings suggests that wind farms underperform due to an overestimation of wind resources, but AWS Truepower says the analysis misses the mark.


SunEdison Buying First Wind In $2.4 Billion Deal

Global solar company SunEdison and its yeildco have announced an agreement to buy the Boston-based developer, a major player in the U.S. wind industry.


U.S., China Reach Ambitious Climate Change Accord

The agreement between the global superpowers leans heavily on the deployment of renewable energy, such as wind and solar.


What The Midterm Elections Mean For The U.S. Wind Industry

Both chambers of Congress are now under Republican control for the first time since 2006. How will wind energy fare?


GE Blade Crashes At Mehoopany Wind Farm In Pennsylvania

The turbine manufacturer says the Nov. 2 incident is "isolated and unrelated" when compared to earlier blade issues.

Hybrid Energy Innovations 2015
Renewable NRG_id1934
BG 2015DblBox_id2032