in News Departments > Projects & Contracts
print the content item

The Oklahoma Corporation Commission (OCC) has approved cost recovery for three wind power purchase agreements recently signed by Public Service Co. of Oklahoma (PSO).

The contracts, totaling 600 MW, are for NextEra Energy Resources' Seiling Wind project, TradeWind Energy's Goodwell Wind project, and Apex Clean Energy's Balko Wind project.

According to PSO, estimates show the agreements will reduce customer costs by $53 million in the first year, with annual savings growing over the 20-year length of the contracts.

“These contracts were based on extraordinary pricing opportunities that will provide substantial savings for our customers,” says Stuart Solomon, PSO president and chief operating officer. “Another benefit is the diversity that an additional 600 MW of Oklahoma wind energy will bring to our fuel mix.”

PSO issued a request for proposals in June 2013 seeking up to 200 MW of new wind energy resources. The utility says the decision to contract for an additional 400 MW was based on all-time-low prices for wind power. When deliveries of energy from the three new wind contracts commence in 2016, PSO’s total wind under contract will be 1.137 GW.




Trachte Inc._id1770
Latest Top Stories

The Song Remains The Same: Ontario Seeks More Science Before Lifting Offshore Ban

The Ontario government says the nearly four-year-old offshore wind moratorium will remain in place until the province fully understands the technology’s impact on the environment.


Why States Should Adopt A Renewable Portfolio Standard

A new study analyzes the potential benefits of state renewable energy mandates, as well as recommends what such policies should include.


Sen. Reid Vows To Bring Wind PTC To A Vote By Year's End

Nevada's senior senator provides some encouragement to wind industry advocates during his annual Clean Energy Summit.


Steadily, Wind Turbine OEMs Resume R&D Investment

An increased commitment to research and development will likely lead to wind energy innovation - not to mention a likely increase in patent-protected technology.


Quebec Government Postpones Wind Power RFP; No New Date Scheduled

The request for proposals (RFP) is part of an overall 800 MW wind power tranche that will serve as a bridge to the next phase in the province's energy future.

Renewable NRG_id1934
Canwea_id1984
UnitedEquip_id1995
Future Energy_id2008