Boralex Inc., Gaz Metro and Valener Inc. have announced commercial commissioning of the first 131 MW of the Seigneurie de Beaupre Wind Farms within the projected time frame.

Located in Quebec, the Seigneurie de Beaupre Wind Farms are being built as phases and will total 365 MW. According to the companies, the first 62 Enercon wind turbines are currently supplying energy to Quebec's power grid, and the remaining 141 MW of Phase I is expected to be commissioned within the next few days.

The 68 MW Phase II is slated to be commissioned next year, and a 25 MW community project will complete the Seigneurie de Beaupre Wind Farms in 2015.




Advertisement

Trachte_id2056
Latest Top Stories

Deepwater Hits Financial Close For Block Island Wind Farm, Expects Summer Construction

The Providence, R.I.-based offshore wind developer becomes the first to financially close on a U.S.-based offshore wind project.


More Investors Entering Tax Equity Market; Returns Holding Steady

The entry of new tax equity investors to the wind space last year re-ignited an old debate.


Report: Top 10 Turbine OEMs Had Record Year In 2014

Preliminary findings suggest Vestas reigned supreme again among the world's leading wind turbine makers. How did some of the other OEMs fare?


AWEA's Gramlich To FERC: Additional Transmission Needed Regardless Of Clean Power Plan

To further build a more balanced and reliable electricity portfolio, the U.S. needs to build more transmission capacity.


Getting A Grip On Grinding Gearboxes: Why Such Events Need Not Be Showstoppers

Despite advances in gearbox reliability - namely, from condition monitoring systems and greater design standardization - challenges remain.

Hybrid Energy Innovations 2015