Boston-based First Wind Energy LLC, which is developing high-capacity wind generation projects in central New Mexico, has signed a letter of intent to reserve up to 1.5 GW of transmission capacity from the SunZia Southwest Transmission Project.

According to developer SunZia Transmission LLC, its extra-high-voltage transmission project will help enable the delivery of energy, including renewable resources, to customers in the Desert Southwest.

The system will span approximately 500 miles between Arizona and New Mexico. It includes up to two new 500 kV transmission lines and five electrical substations that will provide up to 3 GW of new capacity. Once all permits have been obtained, SunZia says final design and engineering, acquisition of rights-of-way, and construction are scheduled to begin in 2014, with initial operation scheduled by 2016.

“Wind is one of New Mexico’s valuable energy resources. If SunZia can resolve its siting challenges, First Wind plans to accelerate the development of this project in central New Mexico,” says Kurt Adams, First Wind’s executive vice president and chief development officer.

The Bureau of Land Management has led the preparation of an environmental impact statement (EIS) on the SunZia project since May 2009. The final EIS was issued by BLM in June, and SunZia says it expects a record of decision by October. The issuance of this decision will culminate nearly five years of environmental study and examination of the project, the company adds.




Trachte Inc._id1770
Latest Top Stories

Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.

Canwea_id1984
Renewable NRG_id1934
Tower Conference_id1965