in News Departments > Projects & Contracts
print the content item

Siemens has installed the HelWin1 offshore platform in the North Sea, which will link the 295 MW Nordsee Ost and 288 MW Meerwind offshore wind farms to the German mainland.

Using the Siemens technology installed on the platform, the alternating current (AC) power generated by the wind turbines will be transformed into direct current for transmission onto land. The land-based station, also supplied by Siemens to TenneT, is located northwest of Hamburg in Büttel, where electricity will be converted back into the AC power required for feeding into the grid.

"With the installation of our platform at sea, we have successfully mastered the most critical part of this project and are now in the final stretch for commissioning in 2014," says Siemens’ Karlheinz Springer.

The network operator TenneT contracted the consortium consisting of Siemens and the Italian cable company Prysmian for the HelWin1 offshore grid connection in 2010. This consortium is implementing a total of four North Sea grid connection projects for TenneT: HelWin1 and HelWin2 off of Helgoland, BorWin2 off of Borkum, and SylWin1 off of Sylt.

After seven days of transport at sea and four days of installation on site, the HelWin1 platform was anchored at its final position northwest of the island of Helgoland on Aug. 23. Siemens had installed the platform's support substructure at this location in June in the 23-meter-deep North Sea. Now, the two subsea cables from Prysmian are also to be connected.







Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015