RES Americas has filed a lawsuit in Pennsylvania against BP Wind Energy and Mehoopany Wind Energy LLC (MWE), a joint venture between BP and Sempra U.S. Gas & Power.

RES claims the defendants owe the contractor over $55 million in additional expenses accrued in a rush to get the Mehoopany Wind Farm live on Dec. 31, 2012 - just in time to qualify for the wind energy production tax credit (PTC). MWE owns the 141 MW wind farm, located in Wyoming County, Pa., and BP is the operator. The project features 88 GE 1.6 MW wind turbines spread across a 9,000-acre site.

Work on the project was originally slated to begin in October 2011 and end by October 2012. However, RES says the project was delayed from the onset and full construction did not start until February 2012, followed by a series of holdups along the way to completion.

Doug Kilday, the Texas-based lawyer representing RES, says the contractor ultimately documented 272 days of delays and had to squeeze the project from a 12-month process into a five-and-a-half-month period to meet the PTC deadline.

“Each subsequent delay, whether it be a week, two weeks or two days, had a substantial impact because of the initial four-month delay,” Kilday tells NAW, adding that RES believes BP and MWE were to blame for a slew of issues.

For example, RES claims BP and MWE did not provide the contractor with proper permits in the necessary time. In addition, Kilday says RES was hindered by road restrictions and a lack of site access, as well as “unforeseen subsurface conditions” that were not included in MWE’s geotechnical report.

These “crippling delays” and the subsequent time crunch meant that RES had to bring in additional subcontractors and have workers work long hours, holidays and weekends, Kilday adds. RES says the additional costs added up and believes they are the responsibility of BP and MWE.

When reached for inclusion in this story, BP Wind Energy respectfully declined, saying, “The company does not comment on pending litigation." Sempra, which has a half-stake in MWE, did not respond to requests.

However, according to the companies’ response to the lawsuit, as cited in a Sunday Dispatch report, MWE and BP Wind Energy maintain that the extra costs and delays are the result of “RES’ own self-inflicted performance issues.”

In addition, BP Wind Energy and MWE have filed a lawsuit of their own against RES Americas in Texas. The companies are seeking up to $32 million in damages.


Trachte Inc._id1770
Latest Top Stories

Quebec Government Postpones Wind Power RFP; No New Date Scheduled

The request for proposals (RFP) is part of an overall 800 MW wind power tranche that will serve as a bridge to the next phase in the province's energy future.


Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.

Canwea_id1984
Renewable NRG_id1934
UnitedEquip_id1995
Tower Conference_id1965