After more than a year of preparation and near-shore testing near Atlantic City, N.J., offshore wind developer Fishermen's Energy says it relocated a Wind Sentinel buoy to an offshore area leased from the U. S. Department of the Interior's Bureau of Ocean Energy Management (BOEM).

Located 11 miles east of Ocean City, N.J., Fishermen’s Energy notes the site is within the Mid-Atlantic wind energy area, where the company intends to build a 350 MW offshore wind farm.

Deploying the buoy in federal waters required approvals from BOEM, the U.S. Coast Guard and the Army Corps of Engineers, explains Stephen O’Malley, Fishermen’s director of metocean assessments. The primary system in the Wind Sentinel is a LIDAR wind measurement device that provides information on wind speed, direction and shear from the water surface to a height of nearly 500 feet.

With approvals in hand, he says, Fishermen’s Energy contracted with Claremont, N.J.-based Northstar Marine to build the anchoring system and install the Wind Sentinel system.

"The device is now operating in 65 feet of water and transmitting environmental and meteorological data back to Fishermen’s offices to support wind farm design and development," says O'Malley.

Fishermen's says the Wind Sentinel is equipped with environmental monitoring sensors that are installed on a buoy platform called the NOMAD. Developed by the U.S. Navy in the 1940s, the NOMAD is a reliable platform still used by major oceanographic research institutions.


Trachte Inc._id1770
Latest Top Stories

Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.

Renewable NRG_id1934
Canwea_id1984
UnitedEquip_id1995
Tower Conference_id1965