Gamesa says it has completed the main assembly of Spain's first prototype offshore wind turbine, located at the Arinaga Quay in Gran Canary Island.

According to Gamesa, the tower, nacelle and blades were shipped from Bilbao port to the Canary Islands. The tower measures 90 meters and is made by Windar, a joint venture between Gamesa and Daniel Alonso.

The nacelle measures over 12.5 meters long and is 4 meters tall and wide. It weighs 72 tons. Once the nacelle was hoisted onto the tower, work began to assemble the three blades, each of which measures 62.5 meters long and weighs 15 tons, making them the longest blades ever produced and transported in Spain.

Gamesa will now begin the turbine’s electrical assembly and grid connection work. It expects the turbine to achieve certification by the end of the year, with installation of the first units in 2014.

This offshore turbine, with a rotor diameter of 128 meters, ensures reliability and maximizes energy output, notes the company, adding that it has invested more than half a million engineering hours in the turbine's design process.


Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015