Turbine manufacturer Gamesa has signed an agreement with Consorcio Morrinhos to supply 75 of its G97-2.0 MW wind turbines for five wind projects being built in Brazil in the town of Campo Formoso in the Bahia state.

Gamesa expects to start installing the wind turbines in the second half of 2014 and finish by the first half of 2015. Under the agreement, Gamesa will also handle operations and maintenance at all five wind farms for a period of 15 years.

Wind farm construction will generate 870 direct and indirect jobs. Once operational, the projects will produce around 727,000 MWh of electricity a year, Gamesa notes.


Trachte Inc._id1770
Latest Top Stories

Wind And Solar Are Catching Up With Nuclear Power, Says Report

A new report from the Worldwatch Institute says nuclear energy's share of global power production is steadily shrinking. Meanwhile, renewables' share keeps growing.


Could New Desert Plan Spell The End Of California Wind Energy Development?

The California Wind Energy Association says it is disappointed with the draft Desert Renewable Energy Conservation Plan, which was recently released by state and federal agencies.


New U.S. House Bill Includes Wind PTC Extension

U.S. representatives have introduced the Bridge to a Clean Energy Future Act of 2014, which would extend the production tax credit (PTC) and other provisions through 2016.


Utility-Scale Wind And Solar Keep Getting Cheaper

A new study measures the levelized cost of energy from various technologies and suggests that the costs of utility-scale wind and solar power are catching up with those of traditional sources, even without subsidies.


The Song Remains The Same: Ontario Seeks More Science Before Lifting Offshore Ban

The Ontario government says the nearly four-year-old offshore wind moratorium will remain in place until the province fully understands the technology’s impact on the environment.

Renewable NRG_id1934
Canwea_id1984
Future Energy_id2008