Illinois-based Midwest Wind Energy (MWE) will no longer actively develop wind farms and has sold the majority of its project development portfolio to Minnesota-based Geronimo Energy.

Michael J. Donahue, executive vice president of MWE, tells NAW that the company began searching for an alternative source of funds about 18 months ago, after losing capital from long-time joint-development partner Edison Mission Energy.

“The hardest capital to come by today in the industry is the risk money that comes with developing projects from scratch,” he says. “We had partnered with Edison seven-and-a-half years ago to provide us with a development loan structure that funded all of our development activity. That aspect of the relationship changed when Edison had to curtail the development funding on its entire wind portfolio - not just Midwest Wind Energy - as a result of an internal financial situation.”

Donahue says his company’s relationship with Edison “continues to be excellent,” but MWE was left with two choices: find another joint-development partner to help fund and complete MWE’s portfolio, or sell the portfolio.

After exploring several options, the company set its sights on Geronimo Energy in fall 2012, and on March 26, 2013, the two parties announced that Geronimo would acquire substantially all of MWE’s portfolio.

“At the end of the day, Geronimo demonstrated a strong source of development funding and expertise,” Donahue explains. “Our primary objective was to keep our portfolio viable and moving forward.”

The acquisition
Through the deal, Geronimo purchased eight wind development projects representing a total potential capacity of over 1 GW. The portfolio includes the 400 MW Grand Prairie wind farm in Nebraska and the 210 MW Walnut Ridge wind farm in Illinois. Financial terms of the acquisition were not disclosed.

Blake Nixon, president of Geronimo Energy, says it was a strategic acquisition to help broaden the company’s portfolio and enter new markets, especially in Illinois.

“Illinois is a large market, not only from the utility side, but also from the commercial-customer perspective,” Nixon says. “There are a lot of great corporate headquarters in Illinois, Chicago in particular. We see a lot of attractiveness to the Illinois market.”

In addition, Nixon considers several of the portfolio’s projects construction-ready. “We think that the projects are very well developed,” he says. “Midwest Wind Energy selected good sites that are competitive and can offer real viable options for buyers.”

Geronimo has also hired “a substantial number” of employees from MWE. Nixon says having members from MWE’s development team on hand was necessary to continue with the portfolio’s progress and create a seamless transition. 

“This was almost like a merger,” Donahue adds. “One of our top priorities was that if we were going to transfer the assets, we wanted to transfer the key staff along with the assets - that was one of our major objectives in finding a suitable purchaser.”

What’s next?
MWE has retained the 75 MW Broken Bow II project in Nebraska because of a current power purchase agreement, as well as a few minor assets that Donahue says will likely wind down over the next several months. However, now that MWE has sold most of its portfolio, the company will remain as an entity but not actively develop wind projects.

Donahue says that he and partner Stefan Noe, president of MWE, still have some contractual rights to the projects purchased by Geronimo, as well as to other projects that the company has worked on over the years.

“We’re basically going to be maintaining our contractual relationships and deriving income,” he explains. “We will not be actively out prospecting for new sites. We will not be developing a new portfolio. We want to basically support the portfolio we transferred to Geronimo. If those projects are successful, Midwest Wind Energy will derive an economic benefit.”

Geronimo is already moving ahead with its newly purchased projects. “We have begun the transition and are continuing to develop the projects as is appropriate,” Nixon says. “We’re marketing the projects to customers for power sales, as we are the rest of our portfolio.”

He says Geronimo will continue to seek new opportunities for the company to grow.





Trachte Inc._id1770
Latest Top Stories

Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.

Renewable NRG_id1934
Canwea_id1984
UnitedEquip_id1995
Tower Conference_id1965