NextEra Energy Resources held a dedication ceremony this week for the company's Limon I and II Wind Energy Centers.

The 400 MW facility, located about 90 miles southeast of Denver, comprises two 200 MW projects that are spread across more than 55,000 acres in Colorado's Arapahoe, Elbert and Lincoln counties.

Each project consists of 125 GE 1.6 MW wind turbines. In addition to the wind farms, an approximately 45-mile-long, 345 kV transmission line was built to interconnect the wind farms to the Missile Site substation in Arapahoe County.

The projects are owned and will be operated by affiliates of NextEra Energy Resources. All of the power from both projects is being sold to Xcel Energy under long-term contracts.

"Wind energy harnessed in Colorado and across the country has to be part of any true all-of-the-above strategy that moves us closer to energy independence," said U.S. Rep. Cory Gardner, R-Colo. "That is why we should extend the production tax credit to promote wind energy that leads to private-sector investment like this one, new manufacturing jobs and a clean source of domestic energy.”



Trachte Inc._id1770
Latest Top Stories

Wind And Solar Are Catching Up With Nuclear Power, Says Report

A new report from the Worldwatch Institute says nuclear energy's share of global power production is steadily shrinking. Meanwhile, renewables' share keeps growing.


Could New Desert Plan Spell The End Of California Wind Energy Development?

The California Wind Energy Association says it is disappointed with the draft Desert Renewable Energy Conservation Plan, which was recently released by state and federal agencies.


New U.S. House Bill Includes Wind PTC Extension

U.S. representatives have introduced the Bridge to a Clean Energy Future Act of 2014, which would extend the production tax credit (PTC) and other provisions through 2016.


Utility-Scale Wind And Solar Keep Getting Cheaper

A new study measures the levelized cost of energy from various technologies and suggests that the costs of utility-scale wind and solar power are catching up with those of traditional sources, even without subsidies.


The Song Remains The Same: Ontario Seeks More Science Before Lifting Offshore Ban

The Ontario government says the nearly four-year-old offshore wind moratorium will remain in place until the province fully understands the technology’s impact on the environment.

Renewable NRG_id1934
Canwea_id1984
Future Energy_id2008