in News Departments > Projects & Contracts
print the content item

In an effort to boost grid reliability and capacity, Xcel Energy plans to upgrade the high-voltage transmission system in Amarillo, Texas.

Between now and the end of 2013, the utility will spend $33.6 million to complete projects that will add and update transmission facilities in north, east and south Amarillo - areas where the city is outgrowing the existing transmission infrastructure as electricity demand increases, the company notes.

The 2012-2013 transmission enhancement projects in Amarillo include the following:

North Amarillo. Load growth led the company to build the new Rolling Hills substation on Cherry Avenue, and to upgrade the capacity at the existing Hastings substation. In addition, a new 230 kV transmission line will link the two substations.

East Amarillo.
To improve power flow into east Amarillo, an existing 69 kV line from East Plant substation on Northeast Third Avenue will be upgraded to 115 kV and connect to the upgraded Hastings substation.

South Amarillo. Upgrades to the Randall County substation southeast of the city will accommodate a new 230 kV line that will run southwest to the existing Amarillo South substation. Additionally, the company recently completed a rebuild of a 115 kV line running 58 miles from the Randall County substation to the Kress substation north of Plainview.

Beyond 2013, Xcel says additional transmission enhancements are being studied for the western edges of Amarillo.



Trachte Inc._id1770
Latest Top Stories

Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.


IRS Issues More PTC Guidance, Easing Some Wind Industry Concerns

The Internal Revenue Service (IRS) addresses how much work is needed on a wind farm to satisfy production tax credit (PTC) eligibility.


Embryonic No More: U.S. Offshore Wind Industry Gaining Momentum

After a decade of fits and starts, the industry is moving closer to installing the first generation of wind projects off the country's shores.


AWEA: U.S. Installs 853 MW Of Wind In First Half Of 2014

The American Wind Energy Association (AWEA) reveals the U.S. industry's progress thus far this year and underscores the importance of policy certainty.

Renewable NRG_id1934
Canwea_id1984
Tower Conference_id1965