Vestas has signed a contract to provide eight of its V112-3.0 MW wind turbines to Fri-El Green Power SPA for the Gorgoglione Guardia Perticara wind power plant, to be located in the Basilicata region of Italy.

The contract comprises the delivery, transportation, installation and commissioning of the turbines; a VestasOnline Business SCADA system; and a five-year service and maintenance Active Output Management 4000 agreement.

Delivery of the turbines is expected to start at the beginning of 2013, and the project is expected to be commercially operational by the first quarter of 2013.



Trachte Inc._id1770
Latest Top Stories

Wind And Solar Are Catching Up With Nuclear Power, Says Report

A new report from the Worldwatch Institute says nuclear energy's share of global power production is steadily shrinking. Meanwhile, renewables' share keeps growing.


Could New Desert Plan Spell The End Of California Wind Energy Development?

The California Wind Energy Association says it is disappointed with the draft Desert Renewable Energy Conservation Plan, which was recently released by state and federal agencies.


New U.S. House Bill Includes Wind PTC Extension

U.S. representatives have introduced the Bridge to a Clean Energy Future Act of 2014, which would extend the production tax credit (PTC) and other provisions through 2016.


Utility-Scale Wind And Solar Keep Getting Cheaper

A new study measures the levelized cost of energy from various technologies and suggests that the costs of utility-scale wind and solar power are catching up with those of traditional sources, even without subsidies.


The Song Remains The Same: Ontario Seeks More Science Before Lifting Offshore Ban

The Ontario government says the nearly four-year-old offshore wind moratorium will remain in place until the province fully understands the technology’s impact on the environment.

Canwea_id1984
Renewable NRG_id1934
Future Energy_id2008