San Diego Gas & Electric's (SDG&E) Sunrise Powerlink renewable energy transmission line was officially dedicated during a ceremony at the new Suncrest Substation, which is a key component of the Sunrise Powerlink.

The 117-mile, 500 kV transmission line will carry clean energy from wind farms and solar projects in California's Imperial Valley to San Diego and enable SDG&E to increase the amount of renewable energy it delivers to customers.

SDG&E has signed eight power contracts for more than 1 GW over the past several years for wind and solar energy in Imperial County. Two of these projects are now under construction.

After a five-year environmental review and permitting process, SDG&E broke ground on the transmission project in December 2010. On June 17, the transmission line was fully energized, and control was officially transferred to the California Independent System Operator.

"While the Sunrise Powerlink will serve as a major conduit for renewable energy in the near future as those solar and wind projects are constructed and put into service, this transmission line is providing this region with real benefits right now," says Jessie J. Knight Jr., CEO of SDG&E. "With a major power plant in Southern California currently out of service, the Sunrise Powerlink is playing a major role in boosting electric reliability and alleviating potential energy shortages."

The Sunrise Powerlink also features six miles of underground 230 kV cable and a 40-acre, 500 kV transmission substation.


Mortenson Construction_id2024

Trachte Inc._id1770
Latest Top Stories

Wind And Solar Helped California Grid During Challenging Summer

According to the California Independent System Operator, the state suffered from heat waves and drought this year, and wind power played a "significant role" in keeping the lights on.


Recapping The Wind Industry's Third-Quarter Deals

Mercom Capital Group recaps investment and merger and acquisition activity during July, August and September.


Yearly Installed Capacity Figures Already Beat 2013 Numbers, More Wind On The Way: AWEA

While the American Wind Energy Association (AWEA) lobbies Congress to extend the production tax credit, the association notes wind projects now under construction signal a vibrant 2015.


Yahoo Inks Contract To Buy Kansas Wind Power

The Internet company plans to log in to the Alexander wind project, which is being built by community developer OwnEnergy.


Could Initial Offshore Wind Projects Crash New England's REC Market?

Some are concerned that the first offshore wind projects could negatively impact pricing of renewable energy credits (RECs) in New England.

Hybrid Energy Innovations 2015
Renewable NRG_id1934
BG 2015DblBox_id2032
Canwea_id1984